Dard, | don't know Nyou received my response an the 25" but l want to make sure Vou are aware that | ari taking
care of your concerns. On the 25’? laweote that we will Incormorate the drawing modifications into an
addendum. Once the addendum is distributed we willce the MOEO.
‘This should address jrenis 2 and 3.
Dadi ete PDF of the final POR and provide @ hand cony and tigital coy for your use.
Matt,
Based on our review, the following isaues remairy
a) The Engineers response to our comment #3 indicated that the PDA had been corrected, However, we did
nol receive an updated copy of the POR, and thus have no way te confi thet ib was corrected,
2) The Engineers response to aur coranient #6 indicates that the septic tank wes tn be relocated per aur
request, The plans that we received show na change in the location of the septic tank,
3) The detail of the tunk overflow was added buck to Sheet P19, however It contains twa dimensions on the
overflow weir cone that are listed ac "as req'd”, This iscue is the same as that for the sizing of the
tank, MDEC canned issue a permit for “as reas”.
Please note thet | will be oul of the office next week and will return on Agri 7).
Thanks,
Dard J Gotham PE.
Michigan Demernaent of Environmental Quality
Olice of banking Wailer & Municipal Assistance
Saninaw-Bay Distict Ohics
404 Kelchuin Street, Suse b
Bay City Bl 48708
BEO-4250.98 146 (Phone)
BEU-BAT-821 8 (Fae
ee
Sent: Monday, March 24, 2014 6:28 AM
We were crovided the documents from the sanitarian for the intermediate pump station. As shown on the permit the
minimiuan distance is 10 feat. We will have JH address the distance from the pump station as discussed in the review
meeting,
John,
Thought I should give you a update of the olan submittals for the Pipeline Contracts (S.4002, $.4003, 5.4005 and
5.4006). The 60% subrnittals will be as shown on the Planning Calendar with one caveat. They will be submitting only
the glans on thase dates, All the specifications and PDR’s are projected to submitted on or before February 4a i still
will have the plans delivered to Jon and Mike the day after they are received per the Planning Calendar and once we
have received the PDR’s & Specifications, | will see that they are delivered to thern as they are received.
Ary questions, please let me know.
Larry A, Osborn, PE, Professional Engineer
555 S. Saginaw Street, Suite 201, Flint, Michigan 48802
£10.236,2556 direct | S1O.S16.6793 cell | 810.295.4975 fax
xxxEND_PAGE:deq11_b403_1848_1850_1
Mike -Please review and let me know what works for you and MDEQ staff/needs. We will schedule what works
for all do you.
John O'
Athached is the mast up to date schedule. We can now begin to look at the MBEO reviews and how they will
get incorporated.
I believe we had a very productive meeting on the 10th. Covered many issues and developed scheduling that
will be efficient/productive for all concerned and work within the compressed design schedule established to
more the project quickly.
The next meetings, including DEQ staff, are as follows:
-Workshop-November Sth at GCDC at 8:00AM. The first hour, for the DEQ staff, will be devoted to a pipeline
surge analysis presentation,
-Pump Station Review-November 19th at 8:30AM at GCDC office. The 60% PS drawings will be submitted to
GCDC 11/6 and then GCDC_ [WT] to send to both DEQ offices,
-Pipeline Review-January 6, 2014 at GCDC office at 10:00AM, the 60% pipeline drawings to be delivered to
GCDC on 12/13 and then GCDC
[WT] to sent to both DEQ offices.
I was agreed that Larry Osborn will hand carry a flash drive to both the Lansing and Saginaw DEQ offices, of
the 60% plans, to expedite the review process and they to put on a LAN system as appropriate. It was agreed
half size drawings are appropriate at this review stage.
It was further agreed that Larry Osborn will email the pipeline PDR and
Matt has sent the pipeline map.
Any questions let me know.
John O'
xxxEND_PAGE:deq17_b125_1038_1038_1
Matt-The agenda is for the afternoon, pump station, and at GCDC offices. I thought we were meeting off site?
We will need the AM agenda and location/time as well.
Your thoughts.
xxxEND_PAGE:deq17_b124_1035_1037_1
John O'
twill not be available to attend on August 12 and will be out most of that week.
Mike Prysby will just be returning after being off this week, but may be able to attend fater that week.
Steve Ashford may also be available later that week.
Stephen Busch, PE.
Lansing and Jackson District Supervisor
Office of Drinking Vater and Municinel Assistance
MOEQ
547-643-2314
Sorry about the delay, but this is my first day back. 1am: currently scheduled to be out of town on the 12. i have
absolutely no problems with Steve Busch representing the department on the treatment plant issues. If you do get into
the matters involving the transmission line, please invite Steve Ashford as weil.
Jon W Bloamker
On August 12°", | may be in Arizona. Tentatively iam scheduled ta be there from August 11°-16"" as part of a teaching
and consulting job. FH know rruore in a week.
dear
xxxEND_PAGE:deq11_b444_1931_1932_1
John O’Brien ask that | invite you to the next progress meeting for a phase of the Raw Water Supply design. We will be
hosting the meeting on 8-12-13 at 2:00 at our offices. We are going to discuss a potential connections to for the City of
Flint who will also be in attendance with the meeting.
xxxEND_PAGE:deq11_b444_1931_1932_2