RE: RE: Flint Water Age map
- From
- Mike Prysby
Daugherty,
Based upon the most recent information provided to us from the city and your consultant, we
are comfortable with either size transmission main (20-inch or 24-inch) for the transmission
main project. An Act 399 permit (Permit No. W131020) issued March 18, 2013 (expired
yesterday) inlcuded 23,550 LF of 24-inch WM, 1068 LF of 8-inch WM and.6800 LF of 8-inch
WM, Given the reduced scope (lineal footage). of the project and expired permit...A new Act
399 permit seems more appropriate. Also, if the remaining work in the future (to complete
the rest of the project) is completed under a separate contract, then, a separate Act 399
permits needs to be issued for that contract. A revised Act 399 permit application and set of .
plans (reduced scope) are needed. Assuming no changes in actual location of the proposed
watermain and appurtenances, we should be able to expedite the review and issuance permit
in a timely manner.
Michael Prysby, P.E.
District Engineer
Office of Drinking Water and Municipal Assistance
517 290-8817