Contract S-4002 100% and S-4003 90% Submittals - MDEQ comments

We've completed the review of both projects and the only significant issues that resulted were the Leakage Test forrnufas that Mike Pryshy identified in his review of S-4005. When the corrected specs are received, | arn prepared to issue the perrnit for $-4007. ffl have them by early afternoon on Monday, June 23%, Lean bring the permitted plans and specifications to the June 24° meeting. Vn willing to replace the corrected section of the spec inte the previgusly submitted specs if that is easier. Emailing them to me would be fine. Thanks, Daryl J. Gotham, FE. Michigan Denartrnent of Environmental Quality Office of Drinking Water & Municipal Assistance Saginaw-Gay District Office 401 Ketchum Street, Suite 5 Bay Gity, ME 48708 989-420-8146 (Phone) 989-891-9213 (Fax} xxxEND_PAGE:deq25_b161_1514_1515_2

KWA Water Supply System - Updated Surge Analysis

Mike, As discussed in our meeting this morning, please find the updated Surge Analysis dated February 6, 2014 for your information and review. As requested | have copied Jon, Steve and Darrel. Let me know if you have any questions. Larry A. Osborn, PE, Professiona! Engineer 555 S. Saginaw Street, Suite 201, Flint, Michigan 48502 810.235.2585 direct | 810.616.6793 cell | 610.235 4975 fax xxxEND_PAGE:deq11_b405_1852_1852_1

Fwd: FW: Updated KWA Planning Calendar

John, Thought I should give you a update of the olan submittals for the Pipeline Contracts (S.4002, $.4003, 5.4005 and 5.4006). The 60% subrnittals will be as shown on the Planning Calendar with one caveat. They will be submitting only the glans on thase dates, All the specifications and PDR’s are projected to submitted on or before February 4a i still will have the plans delivered to Jon and Mike the day after they are received per the Planning Calendar and once we have received the PDR’s & Specifications, | will see that they are delivered to thern as they are received. Ary questions, please let me know. Larry A, Osborn, PE, Professional Engineer 555 S. Saginaw Street, Suite 201, Flint, Michigan 48802 £10.236,2556 direct | S1O.S16.6793 cell | 810.295.4975 fax xxxEND_PAGE:deq11_b403_1848_1850_1

Re: FW: MDEQ Meetings

DEQ-See the proposed schedule change with plan delivery as well. I am fine with the revised to allow you to review plans, in a timely manner, and then we meet at GCDC on Jan 6th at 10:00AM to review both PS'S, a pipeline and an update on KWA/GCDC, Flint City and status of DWSD. Wishing you all a Merry Christmas and Happy New Year. Go State. Any questions let me know. John O' John, A little change in plans. The alignment for $.4002, $.4003, S.4005 and $.4006 will be moving to the greenbelt. Therefore the 60% plans for this work will not be ready to share with MDEQ as scheduled. Below is what we believe the MDEQ will receive and when. Look this over and if you have any questions, give either Matt or | a call. 16. WaveTam Larry A. Osborn, PE, Professional Engineer 555 S. Saginaw Street, Suite 201, Flint, Michigan 48802 Sent: Tuesday, December 03, 2013 3:47 PM

DEQ Meeting with Flint City

>> >> As per Mike they are going to operate the plant, with softening, starting in April 2014 when the DWSD contract expires. So, they have to move quickly to improve the plant to manage/produce water 24/7. It sounds like the design will proceed quickly to allow 24/7 operation and much is to be done quickly to meet the deadline. | am sure somethings will slip beyond April but they seem to be in a move quick mode! >> | told Mike that they would get the 60% PS drawings by say Friday the 8th as they are closed Monday. Larry, | assume that is correct. >> It appears that moving the meeting to the 21st is going to be OK for review of the PS drawings. They did not seem to have any heartburn with the standards as presented but it will be a good idea to just open that issue up, on the 21st, to be sure it is vetted. >> All seems to progress. >> Any questions let me know. >> John O'. xxxEND_PAGE:deq04_b577_6019_6376_276 Rennaker, Joanne (DEQ)