Jonathan Berman

Senior Project Manger, EQA at DEQ, Office of Drinking Water and Municipal Assistance, Revolving Loans Section / DEQ

11

Emails

Feb 2014–Dec 2015

Archive range

11 emails found.

Genesee County DWRF # 7405-01 (Meters): Comments on Project Plan

To
Unknown recipient
Good afternoon, Dan. Below are my comments on the Project Plan. We ask that you respond to (and/or resolve) these items by January 11th. #1) — Lunderstand the meter replacement map in Appendix B shows the municipalities where new meter installation will take place while the Figure 1-1 shows the actual service area for the county system. Will the entire DWRF project contain meter installation in all 10 townships (i.e. Clayton, Davison, Flint, Flushing, Gaines, Montrose, Mt. Morris, Richfield, Thetford and Vienna) where new meters will be installed? We need you to provide a map which not only shows the municipalities where new meter installation will take place for the entire DWRF project, but also identifies the locations of the proposed five (5) base stations for the entire DWRF project. xxxEND_PAGE:deq16_b5_0892_4900_2420 In answer to the first part of the question, yes, we will be installing meters in all 10 of the townships. In answer to the second part of your question, there is a propagation map in Appendix B showing the locations of the seven towers in the original project. We have installed the base stations at Beecher Tank and Houran Tank. If you need a new map please let me know. #2) Are there no capital improvements and/or replacement costs over the 20 year planning period for keeping the Manual Ready System? Are the no replacement costs over the 20 year planning period to switch to the Meter Replacement and AMR/AMI System? i'm not sure what you mean by " Manual Ready System" ? No, there are no replacement costs anticipated for the 20 year planning period. The new meters, endpoints and base stations have a 20 year life expectancy. #3) a. Lunderstand the entire DWRF project has anticipated impacts to the state regulated resources of floodplains, inland lakes and streams, or wetlands. Confirm. We do NOT anticipate any impacts from the Meter Replacement and AMR/AMI Project. b. Did you obtain clearance from SHPO? We need a copy. SHPO letter is in Appendix J and we received no response #4) a. For the full construction footprint for the entire DWRF project (new meters and antennas), do you conclude that it is in an urban area where no suitable wildlife habitat for state species is present or that the construction work is limited to existing structures? If so, contact with MSU-MNFI can be waived. Otherwise, a Rare Species Review request must be submitted via the MSU-MNFI website (bite //motl any. mou cfm) to generate a letter from MSU-MNFI staff summarizing their findings. Yes, we conclude that The Meter Replacement and AMR/AMI Project is an urban area where no suitable wildlife habitat for state species is present and that the construction work is limited to existing structures. b. For the full construction footprint for the entire DWRF project (new meters and antennas), do you conclude that it is in an urban area where no suitable wildlife habitat for federal species is present, or if construction work is limited to existing structures and in turn the project will have “no effect” on any federally listed species? If so, contact with U.S. FWS can be waived. Otherwise, the U.S. FWS xxxEND_PAGE:deq16_b5_0892_4900_2421 #5) must be followed. Yes, we conclude that Meter Replacement and AMR/AMI Project it is in an urban area where no suitable wildlife habitat for federal species is present, and the construction work is limited to existing structures and in turn the project will have “no effect” on any federally listed species. Are any of the new antennas for the DWRF project located within 5 miles of any licensed airport? If so, how much height will the new antennas add to existing water towers or cell towers? If it is significant, you may need to contact MDOT Bureau of Aeronautics. The new antennas heights are not significant. #6) #7) #8) #9) Will there be any service interruptions? Yes there may be short service interruptions. . If so, what should users anticipate? We have prepared a letter and a FAQ that will go to each customer outlining the process. What hours/days of the week will construction take place? Project work will take place Monday through Saturday during daylight hours with special appointments at other hours to meet customers needs. In a 2"° Quarter schedule, we expect construction to begin by May 2016. Per our telephone discussion you confirmed that we are anticipating a 3rd Quarter Schedule. Based on that we would anticipate construction to begin by July 2016, In turn, when would construction completion be expected? We would anticipate construction completion in July 2018. Will construction result in traffic congestion, limited driveway access, and/or noise? No. If so, describe mitigation. Any dust/soil erosion? No. Will there be any excavation? No. Will a soil erosion permit not be necessary? A soil erosion permit will not be necessary. What permit(s) will be needed for construction? We do not anticipate that any additional permits will be necessary. Will there be an increase to user rates to repay DWRF loan debt? If so, what is the estimated increase to the annual user rate for the typical residential customer? If not, how will DWRF loan debt be repaid? Page 34 leaves this issue unanswered. Note that while we wait for EPA to decide if the project must be re-bid, we will continue use the $5.4 million cost estimate. No, there will not be an increase in the user rate for the project. The existing rates are sufficient to repay the DWRF loan. See Page 34, the last sentence under Section 3.4. Also see the User Rate Analysis submitted on 12-3-2015. Below are selections from the November 2010 EA-FNSI for Genesee County DWRF #’s 7340-01 and 7341-01. Is this information still accurate? Identify any updates in your response. “..Genesee’s water system service area consists of approximately 145,000 residents inside the county. as depicted in Figure A, along with over 8,000 residents outside the county in Birch Run (village and 3 xxxEND_PAGE:deq16_b5_0892_4900_2422 township) in Shiawassee County to the west and New Lothrop in Saginaw County to the north. The Genesee County Drain Commissioner’s Office is responsible for the operation and maintenance of the system. Potable water from the Detroit Water and Sewerage Department (DWSD) is purchased by the city of Flint (Flint), which sells a portion of its supply to Genesee. The actual source of the DWSD water supply is Lake Huron in close proximity to the city of Port Huron. After treatment at DWSD’s water treatment plant the potable water routed for Flint and then Genesee travels through a single 72- inch-diameter water supply main courtesy of the Imlay Pump Station.” “Genesee ’s water system (Figure B) has around 116 miles of transmission and distribution water main ranging in pipe diameter size from 6-inch to 72-inch with approximately 98 percent ductile iron, less than 2 percent cast-iron, and less than 1 percent concrete pipe. Genesee’s other water system components include 6 major pump stations, 21 storage facilities, and 1 standpipe.” See Revised below “ .. Genesee ’s water system service area consists of approximately 145,000 residents inside the county. The Genesee County Drain Commissioner's Office is responsible for the operation and maintenance of the system. Potable water from the Detroit Water and Sewerage Department (DWSD) is currently purchased by Genesee County. The actual source of the DWSD water supply is Lake Huron in close proximity to the city of Port Huron. After treatment at DWSD’s water treatment plant the potable water routed for Flint and then Genesee travels through a single 72-inch-diameter water supply main courtesy of the Imlay Pump Station.” Genesee County is a member of the Karegnondi Water Authority (KWA) which is currently constructing a source water supply system from Lake Huron to Genesee County. Genesee County anticipates switching to KWA water in 2017-2018. “Genesee’s water system (Figure B) has around 543 miles of transmission and distribution water main ranging in pipe diameter size from 6-inch to 72-inch with approximately 98 percent ductile iron, less than 2 percent cast-iron, and less than 1 percent concrete pipe. Genesee’s other water system components include 6 major pump stations, 21 storage facilities, and 1 standpipe.” #10) We need a list of 40 mailing addresses where water bills are actually sent (i.e. we do not want to our postcards returned to us by USPS) which are for customers that will receive new meters/be located near new antennas for the DWRF project. We have attached a list of 40 active accounts with both the connection address and the billing address. Let me know if you have any questions. Thanks. xxxEND_PAGE:deq16_b5_0892_4900_2423 Jonathan M, Berman Senior Project Manager, ERA Michigan Department of Environmental Quality Office of Drinking Water aad Monicipal Assistance Revolving Loan Section Bermant Phone #: 517-284-5400 (note new number) Fax #: 517-373-4797 (note new number) Constitution Hall ~ 4" Floor South (note new floor location) $25 W, Allegan Lansbig, ME48933 for deliveries} P.O. Bos 30241 Lansing, ME 48909-7742 Gnailine} DWRF website: wyw inichigan xxxEND_PAGE:deq16_b5_0892_4900_2424 90T8P yOeuy NNV L8ET XOU Od inns M1OLSIa SLEE ANtIS LHONSAV OTHZ6E0OOO-Z] TY | CLS60 SOIdV¥ GNVHS | 8 41S 3S LONOWLObA> ANI S N3GNIT SS7Z SNOLLN10S SSINISNG ALINDILNI OTTZ6E0000-2] OF | L0S87 ANI GY ATNYOL OL7P ANI ATMHOL OL77 NIVW LJveoulyY NYTIS1D OW 06696£0000-2] 6E T4ci4 aNnvyund 801 XOB Od inns NONN318ZEE NOINN LId3¥D YNITJOVS oz696e0000-2| 9¢ | E2887 ONISNV1 LSV3 8T@b XOd Od ANIIS 'S N3GNI1 OSOE O71 ‘AW 4 3GAZ 3 3DYOIO. 01696£0000-¢| Z€ 60687 ONISNYT OObOE XOB Od inns MATIN 0627 O71 ¥3LN39 TIVLIY LaSY3WOS IW. otes6e0o00-z| 9¢ | LOS87 ANII YG JONVHDXI Zh7S ANI JONVHDXI ZHzS AAC 02296£0000-¢| SE OES6D Sdidv¥ GNVYD | aS NOSYALLV¥d OOES AN YSTIIW 8E0S OTT NVILSISHD AIS OZZS6E0000-2} 7E £0587 inns GY MATIN SLT inns GY MITTIN SZTH DOSSV GTYOM JYNSIST osts6e0000-z| ¢¢ | LOS87 ANIS SUG WuvdulY OZ0E| ANINS SUG WuVdul¥ OZ0E | 09 LNIWdINDI ODN ogev6£0000-¢| Ze L0S87 ANd Yd AVGNOH Ter) Ann AVGIIOH T27p ONIS¥I1 YFTIVYL SNOOD OELEGEONOO-Z| s0Tsy yOeuy NNV OO€ ALS AMd YSMOHNASIS J SOE, inns ADNWHOX3 S775, ONIdNOYS SNOILNIOS LANYILNI oave6eooo0-z[ 0¢ | eevey ONIHSN14 GY ONIHSN14 OSTS ONIHSN14 ONIHSN14 O9TS AddOHS WV3¥D 3918 Yvd ONIN 02626£0000-¢| 6z, €0S8b ANI 1S LYNOD MTZ) ANI THW TOTZ ONIWGL os9z6£0000-Z] gz | Itsy aTNA31138 GY ALYADOVH OO6ZT inns AWONOH TOTH | O77 S4Sl¥dY3.LNJ HOVE! o8zo6e0000-2| Zz | ‘8bS6r SdIdVY¥ GNVHS | ZAS ‘ISHI1PS 68) ANII4 S AMH MIONITIVE STEZ LN3WdINDI TWOIGIW LYVH 0€€68£0000-| 9z, cESsy inns GY VNNNYOD 62TP9| inns YNNNYOD 62TH YL HSVM YV2 8 38017 NIND DVIS YINDIHD ozge8e0000-2| Sz | Ovg8y ONVIGIW AS NIVIN J EEE) ANI S N3GNIT TOSE NY TYDIINFHD 05528£0000-| pz. L0S87 ANI YG AVOIOH 8977) ANI bud AVGIOH 8977 SIDIAYIS GILIGIdXA XLV O90PSEO000-Z} €Z eLpsy IID ZLYVMS GY S13 6EZE AIAN ZLYVMS: S SIW13 6EZE 09 344509 JGISIUIS otvoseooo0- zz | TESsy ANI SEZOTE XOd Od NII ONIHSN14 ELSE ONI SN3HD LI L4VYDGOOM OTvSZZ0000-Z| 68087 Naga GY SNIHdILS SZZZT ANI GY AFNYOL LPEE O71 LYOdSNVYL TWHLNID 0¢gzto00c0-2] 02 | eersy SNIHSN1S 1 ANNYG 209) SONIHSNIS YAAIY ZTOL | D1v JOGIY YSAIY ostp9zo000-rt| 61 | TLEC-E€v8b ONIHSN14 Yd JDYIWINOD 2907 ONIHSN14 JYINWWOD £907 S1LONGOYd ILFYDNOD WHLN3D 0¢95S20000-rT| QL Ovpc-OT766 ANVAOdS Ovpz XOd Od ANI MNOSY3ld T8b7 ALIMDV4 0/9 09 JYLL LNNOISIC QSZSZZG000-FT} ZL SSOb-vEBTS aTANVG SSOv XO8 Od SONIHSN1S A\NOSY3Id TOSS ALIMILN-JT8VA¥d SLNNODIV IDS ortszzoo00-rt{ 91 | ELb?-€€v8pr ONIHSN14 ‘Id NOSY3ld 62VE ONIHSN14 ‘Id NOSY3ld Teve ONIFDIANIS MVHS: WZ68190000-bT| GL ETbpC-EEvsy ONIHSNTS Id NOSY3Id 6Z7VE ONIHSNTS Id NOSY3Id TPbE AYINVIB 335IOD 0268v90000-rT| FL | bLbc-Eevey ONIHSN14 T 41S 1d NOSH4ld 9SVE ANI AMA NOSYAld S/TH LNIT4 40 SdOHS H31S4NW ASIN 08€8790000-rT| 1 9@bb-LOSBy ANI GY MYNIDVS S STES. ONIHSN1S NNY P9ove O11 SALLY3dOUd ILVAS GERPySC000-FT s0ery NOW veMOL L33uLS NIVIN “S 90T SONIHSN1S A\NOSYAId 7579 ANVE LYN Lsuld o9zeegoo00-rtl LT | bossy ANII GY NOSY3ld TISED ANI M\NOSY3ld TISE: ulvd3¥ OLNY SNO13G 0%26290000-rT| OL ECET-POS8PD ANI YG NV100 0407 AN NV10d 0407 WLIW 133HS NVYSIHDIN ozozos0000-rt| 6 | eersy SONIHSN1S Gy NOSYAId M EOS SINYOIN LW OND 9808) NOISITI09 Jdtdd OLAV oteoosco00-rt|¢_| bossy ANIS ZT ALS AMH Y3ONITIVE N TST ANINS @ 31S YZV1d OID £0ve O71 3SIHdYFLNI IMNSVINL os000s0000-rt| 2 | ESET-POS8PD AN JAY YNIGVS¥d M ZZbE Ann MYNIGVSVd ZZbE| J91Vd YNHLYY otzpssooo0-rt| 9 | poser inns OND 6rbS: inns OND 6rbS) QTYOM YaddOL SdITIHd orezosoooo-rt| ¢_| Ofvsr NOINI4 4AW1NG NVILVHD ST ANI AMV NOSY3ld SZE 41V1S3 1V4¥ INIT Sf ogv2to0000-rt| Fr | SEET-POS8b ANS GY NOSYAId M OSOP ANI AM\NOSYa3ld OSOP VZV 1d NOSYJId osoztooo0e-rt| ¢ | OEOTZ AITIVA INNH dy Wid Y3AV4d 90Z0T AMA NOSYAld E9¢€ dNOYS LSYIGVOUE HIVTONIS ozztto00000-rt| Zz | ssouppy Suievy 358JPPY UOIIE90] @WeN JaWOIsND xxxEND_PAGE:deq16_b5_0892_4900_2425

MDEQ Communications Outreach Team: Nov 12 meeting notes

Follow Up Flag: Follow up Flag Status: Flagged Good afternoon, The Communications Outreach Team had its November meeting this week on Thursday (11/12). It had been several months since the previous meeting. Attached are the notes with the division-level content, etc., including what I offered from ODWMA. The next meeting is 12/10. Let me know if you have questions/requests for the Communications Outreach Team as well as if/when you have updates on what is currently making news (other than Flint drinking water) or has the potential to make news for me to share. Thanks, Jonathan

RE: Communications Outreach: Updates for ODWMA News

Well, the Flint situation is certainly not a “good naws” story and the media is well aware of it. But it sounds like it may be an appropriate sublect for this effort. | provided the following summary earlier today in a response to sorne EPA staff in Region S that do not work in the drinking water program. Last spring, the city of Flint decided to begin relying upon the Flint River as their source of drinking water using a treatment plant that was designed to do so. Last sumrner, the city experienced difficulties with siagnation in some areas of the distribution systern due to significantly reduced demands resulting from the loss of a significant percentage of their residential and industrial demands that accelerated over the last decade. During the surnmer of 2074, they alse had a couple of monitoring periods where they detected total coliform at monitoring ses in inese stagnant areas, and one time they detected E.coli present. The ensuing boil water advisories and public notification heightened custorner concern about the quailty of drinking water and the switch frorn Detroit to the Flint River. Detroit supplied Flint with drinking water from Lake Huron, a much higher quality source than the Flint River. However, monitaring of the Flint water treatment plant tap has never indicated unacceptable water entering the distribution system. In response ta these coliform detectians and in an effort to prevent 4 recurrence, the cily also increased flushing water mains in low flow areas and they have atlernpied to ensure the presence of a chlorine residual throughout the distribution system. Compounding the problem of customer confidence was the results of inilial rnonitering for disinfection byproducts under the Stage 2 Disinfection Byproducts Rule. The initial monitoring reported significantly elevated levels of telal tihalornethane (TTHM) compounds throughout the city’s distribution system. Our district office advised the city that they needed to immediately implement operational techniques at the treatment plant and in the distribution systern to reduce the fornation of these compounds. The steps the city has taken have been successful and have reduced TTHM concentrations to the point where the latest results are below the drinking water standard. However, the standard is calculated on a running annual average and i is likely to be ancther 3 to G months before the annual average at each monitoring siation will (hopefully) meet the standard. Until then, the city has to continue to provide quarterly oublic notification, which will continue to concem residenis despite the iatest TTHM results. xxxEND_PAGE:deq21_b558_1578_1580_1 The switch to the Flint River, the micrabiolegical problems, and the slevated TTHM concentrations experienced jast year have caused a high level of customer dissatisfaction and distrust in Flint. The city is working diligently to resiore that confidence, bul # will not be accomplished easily or overnight. The city’s switch to the Flint River is an interim measure intended to last only until a 72-inch pipeline from Lake Huron fo the Flint water treatrnert plartis cornpleted. itis currertly under construction and expected to be in operation in mid- 2016. At that point, the city's drinking water should again be very similar in quality to what they were receiving

RE: Communications Outreach: Updates for ODWMA News

The audience is the DEQ Communications Outreach Team for next week’s meeting to share information between divisions. It could be a list highlighting newsworthy items (regardless of media coverage), including “hot topics” or proactive good news stories you want the communications office to help package to media/stakeholders. It does not need to be highly technical, but for internal purposes it could be more so then for a general audience. Karen Tommasulo sometimes has ideas for media strategy that we can bring back to our divisions for development on any news item.

Communications Outreach: Updates for ODOWMA News

Richard/Carrie, Do you have updates on what’s currently making news or has the potential to make news for your sections? Richard, I'm guessing Flint’s drinking water is on your list. Thank you in advance for your time and effort in making your contributions. ML Berman Senior Project Manager. EGA Michigan Depariment of Environmental Quality Office of Drinking Water and Municipal Assistance Revolving Loan Section Bermanjenmichigan. 2ov Phone #: 517-284-5400 (note new number) Fax #: 517-373-4797 (note new number) Constitution Hall ~ 4" Floor South (note new floor location) S28 W, Allezan Lanshig, ME48933 (for deliveries} xxxEND_PAGE:deq21_b559_1581_1583_2 OWREF website SRE/SWOQIP webstte: xxxEND_PAGE:deq21_b559_1581_1583_3

RE: Genesee Co. DWRF # 7341-01 (Dalton Subdivision): Scope of Work - 4th Quarter

FY 2015 Jonathon, The Staternents in our 2/27/14 e-maif still hold true below. No changes in scone are proposed. Please let me know if you have any other questions or need any additional information. Lynnette LYNNETTE MEINZ, P.E. Engineer Hl Genesee County Drain Comrnisstaner’s Office Division of Water & Waste Services G-46510 Beecher Road Flint, ME 48532 870 PHONE BEG PA2977S tax

RE: Genesee Co. DWRF # 7341-01 (Dalton Subdivision): Scope of Work - 4th Quarter FY 2015

Hi Lynnette, Per the signed milestone schedule, today (1/14/2015) is the 4th quarter financing target deadline in which to disclose to our office any change(s) outside the MDEQ approved scope of work (if applicable) to the Genesee County DWRF # 7341-01 Phase 2 of 2 Water Main Replacement (Dalton Subdivision) from the 2010 Project Plan and the Environmental Assessment published in November 2010. So, has there been any change(s) or do the statements in your 2/27/2014 email below still hold? Let me know if you have any questions. Thanks. Jonathan M. Berman Senior Project Manager, EQA Michigan Department of Environmental Quality Office of Drinking Water and Municipal Assistance Revolving Loan Section xxxEND_PAGE:deq16_b5_0892_4900_1023 Bermanj@michivan gov Phone #: 517-284-5400 (note new number) Fax #: 517-373-4797 (note new number) Constitution Hall - 4" Floor South (note new floor location) S25 W, Allegaa 348933 Gor deliveries} Lausiag, 2 Lansiag, ME48900-774 1 (mailias} DWARF website: Sent: Thursday, February 27, 2014 2:10 PM

RE: Genesee Co. DWRF # 7341-01 (Dalton Subdivision): FY 2015?

Jonathon: Thank you for your response to DWRF #7341-01 on Thursday, February 20, 2014. To document our phone conversation today, February 24, we offer the following in response to your e-mail: 1. The scope of work for the Dalton Subdivision 8-inch Distribution Water Main Replacement as outlined in the 2010 EA has not changed. The current scope and cost estimate are still valid. 2. The legal entity to issue the bonds is still “County of Genesee”. 3. The watermain is owned by Mt. Morris Township. They will utilize the example resolution that you just e-mailed today. By May 1, 2014, we will send you a copy of the passed resolution, once it is xxxEND_PAGE:deq16_b5_0892_4900_1025 passed. We anticipate sending you a copy of the signed resolution the week of March 10, 2014 (their next available Board Meeting). 4. It is our understanding, if the Project Plan and Environmental Assessment (EA) are not modified, the Dalton Subdivision project would be slated for First Quarter 2015 (which would require Plans and Specs be submitted mid-June 2014). 5. Although a public notice and public hearing are not required, because the Project Plan/EA is not over 5 years old, you recommend a public notice be performed again to inform the residents. We will let you know if we elect to public notice again. Previously, we did not have any public comments come forth out of the public notice or the public hearing regarding the Dalton Subdivision. 6. We may also elect to submit the DWRF — Green Project Reserve Qualification Template for Water Main Replacement and understand it is required to be submitted by the May 1, 2014 deadline also. If any of the above information requires clarification, please let us know. Thank you for your continued assistance with this project. Lynnette LYNIMETTE MEINZ, PLE. Engineer Hl Genesee County Drain Comrnisstaner’s Office Division of Water & Waste Services G-AGLO Beecher Road Flint, Mi 48532 810.732.7370 PHONE BLO732.9773 Fax xxxEND_PAGE:deq16_b5_0892_4900_1026