RE: FDCVT - Preliminary Press Release Info

Terry, Below is additional information regarding the Flint Incinerator also attached is the Incinerator application. Let us know if you need additional information. Thank you. Flint Incinerator The grant project entails shutting down the current Water Pollution Control Facility Incinerator (due to the incinerator not being up to new EPA standards). In order to meet EPA standards, it would cost roughly $8.8M in upgrades to the current incinerator. The grant funding will allow them to replace the functions of the old incinerator by constructing new facilities which will allow for the disposal of waste to landfills. Budget Breakdown Construction Contractor $1,050,000 Project Management $50,000 Total $1,100,000