RE: FDCVT - Preliminary Press Release Info
- From
- Evah Cole
Terry,
Below is additional information regarding the Flint Incinerator also attached is the Incinerator application. Let us know if
you need additional information. Thank you.
Flint Incinerator
The grant project entails shutting down the current Water Pollution Control Facility Incinerator (due to the incinerator
not being up to new EPA standards). In order to meet EPA standards, it would cost roughly $8.8M in upgrades to the
current incinerator. The grant funding will allow them to replace the functions of the old incinerator by constructing new
facilities which will allow for the disposal of waste to landfills.
Budget Breakdown
Construction Contractor $1,050,000
Project Management $50,000
Total $1,100,000