Tom,
Below are the answers to your questions. If you have any further questions, let us
know. Thank you.
Do we know whether Flint has yet applied for any of these (FDCVT) $s ?
ANSWER: We received an application from the City of Flint on September 17". The
amount requested for the project is $2M (the limit for a local unit) and it is estimated to
take $3.1M to complete the entire project. They also indicated that if full funding is not
awarded, it is doubtful that they will be able to move forward with the project. The
proposed project is:
“The city proposes to hire a qualified contractor to provide property assessing
services. Specifically, this contractor will create digital property sketches of all improved
properties, evaluate existing property conditions and improvements by
providing real property data verification, and conduct a comprehensive appraisal
valuation study. This process will take place over a period of 3 years, from June 1, 2016
to July 1, 2019.”
Do we know if they have plans to?
ANSWER: Since they asked for the entire $2M for the above project, we would assume
they are not submitting any further projects, however we are not sure.
And have they asked (& rec’d) $s from this program previously i.e., last year, and If so,
what did they use those $s for?
xxxEND_PAGE:treasury01_b37_6553_6782_200
ANSWER: Treasury awarded Flint two grants in FY 2015 under the FDCVT
program. Treasury has not yet received any reimbursement requests from the
City. Therefore, we have not distributed any of the FDCVT grant related funds to the
City. The two grants are:
Project Name
$1,100,000 | Water Pollution Control Incinerator Shutdown
$900,000 | Water Main Leak Detection Survey and Condition
Assessment
Sent from my iPhone
Brief Description
Water system enhancements thr:
improved waste management
Water system enhancements thr
leak detection and pipe assessme