DWSD Offer Evaluation
- From
- Maxine Murray
- To
- Kevyn Orr
Good afternoon Mr. Orr:
Please find attached a communication from Ed Kurtz.
Thank you.
Maxine Murray
Executive Assistant to
Mayor Dayne Walling
Edward J. Kurtz, Emergency Manager
Michael K. Brown, City Administrator
1101 S. Saginaw Street
Flint, MI 48502
810.237.2035 Telephone
810.766.7218 Fax
(See attached file: Kevyn Orr - April 26, 2013 pdf)(See attached file:
ATT00001 htm)
xxxEND_PAGE:treasury01_b04_0379_0503_110
Crry or Detroit 735 RANDOLPH STREET
WATER AND SEWERAGE DEPARTMENT Detrorr, Micuiaan 48226
Orrice oF Te Director WIWW,DETROIIMI.GOY
RECEIVED
APR 2-9 2013
April 24, 2013
Mr. Andy Dillon, Treasurer
Michigan Department of Treasury
Lansing, Michigan 48922
OFFICE OF THE STATE TREASURER’
Dear Mr. Dillon:
Regarding: Rate Proposal for Flint / Genesee County
As you are aware, during our meeting on Friday, April 20, 2013, the Detroit Water and Sewerage
Department (DWSD) was requested to provide a rate proposal to Flint and Genesee County by
today based upon the specifications that Flint provided to DWSD on Monday, April 22, 2013.
Early this morning, DWSD responded to that request with several documents that were also
provided to your office by electronic communication.
In addition to the proposal document, the State of Michigan requested that DWSD include cost
figures concerning DWSD’s stranded costs associated with capital investment made by DWSD
over the years related to serving both Flint and Genesee County as water customers. This issue
of “stranded costs” has received significant media attention over the past several months, and my
impression is that the State was looking for a clear figure so that there could be subsequent
discussion and negotiation over all costs associated with Flint’s decision on whether to join
Karegondi Water Authority (CWA). -
As you may know, State law requires that public utilities such as DWSD must base their rates
upon the actual cost of service to particular customers. Additionally, state law limits the length
of utility contracts to thirty years, while the useful life of capital assets in the water utility can
greatly exceed that thirty year term.
Unfortunately, the computation of stranded costs for DWSD’s capital investments in capacity
and transmission attributable to Flint’s and Genesee’s consumption of DWSD water, is a
complex calculation that cannot be performed with any level of certainty over the short time
period provided by the State of Michigan for this analysis. Further, I have been advised by
DWSD’s General Counsel that it would not be prudent to engage in a process of trying to
guestimate a price range for such a complex computation.
Iitecstues
a Ae ot
xxxEND_PAGE:treasury01_b04_0379_0503_111
Mr. Andy Dillon, State Treasurer
April 24, 2013
Page 2
Based upon DWSD’s termination of Flint’s existing water contract last week, DWSD has
roughly twelve months to determine the appropriate cost structure for Flint and Genesee’s water
consumption over the remaining term of their non-contracted water service from DWSD.
DWSD will, however, endeavor to finalize the rate impact of the stranded costs by the end of the
current calendar year.
Please rest assure that DWSD’s computation will be in accordance with State Law which dictates
that such rates will not result in a rate structure that would generate a profit for DWSD, Our
intent is simply to compute the rates so that costs properly attributable to Flint and Genesee
County will not be borne by the remaining DWSD water customers,
Sincerely,
Sue McCormick
Director
xe; The Honorable Rick Snyder, Governor State of Michigan
Ed Kurtz, Emergency Financial Manager, City of Flint
Kevyn Orr, Emergency Financial Manager, City of Detroit
James Fausone, Chairman, Board of Water Commissioners
William Wolfson, DWSD General Counsel
Nicolette Bateson, DWSD Chief Financial Officer
xxxEND_PAGE:treasury01_b04_0379_0503_112